Projects

Moma Sands Expansion

From: July 2010
To: December 2011
Cost: $ 198 000 000.00

Scope of our Involvement Aveng E+PC have been appointed as the EPCM contractor to undertake full Project Management and Controls, Engineering Design, Procurement and Construction Management Services for this fast track project. The project has challenging logistics, budget and completion deadline constraints that are being well managed by the ex

  • Read More

  • Nchalo Sugar Mill Expansion

    From: June 2008
    To: March 2009
    Cost: ZAR R 45 000 000

    Project description Illovo Sugar LTD approached Aveng E+PC to prepare a FEP (Front End Package) for the expansion of the Nchalo Sugar Factory from 300 TCH (Tons Cane per Hour) to 330 TCH. On successful completion of the FEP, Aveng E+PC were awarded the EPCM contract to execute the Nchalo Sugar Factory expansion project. The project was compl

  • Read More

  • Matola Fuel Storage Facility Project

    From: May 2008
    To: November 2008
    Cost: EPCM: $ 9.0 million CAPEX: $ 48.0 million

    Upgrade of a Fuel Storage Facility Project description The client engaged the services of Aveng E+PC to develop a Concept Design Proposal and order of magnitude estimate for refurbishment of a petroleum products storage and distribution facility in Matola, Mozambique. The upgraded facility will cater for four different products (gasoline, ga

  • Read More

  • Matola Petroleum Storage Terminal Project - AVEC

    From: March 2008
    To: July 2008
    Cost: CAPEX: R 339.1 million

    Due Diligence for a Fuel Storage Facility Project description AVENG E+PC was engaged to develop a Concept Design Proposal and order of magnitude estimate for a new white products storage and distribution facility in Matola, Mozambique for Independent Petroleum Group (IPG). The facility will cater for three different products (gasoline, gas o

  • Read More

  • Imbani Coal Washing Plant

    From: November 2007
    To: February 2011
    Cost:

    Project description Aveng E+PC Operations were awarded the operating contract for the Imbani Coal Washing Plant, based near Carolina in Mpumalanga, by Worldwide Coal, in November 2007. The design and construction of the plant and infrastructure was undertaken by others. The plant was also previously operated by others, but was placed under care

  • Read More

  • Langer Heinrich stage 2 expansion

    From: October 2007
    To: December 2008
    Cost: ZAR R 454 million

    Langer Heinrich Uranium Mine is presently operating a 2.6 million pounds subsequent to the initial scoping and completing a rough order of magnitude estimate, Langer Heinrich Uranium has undertaken to increase the plant capacity to 3.7 million pounds of Uranium per annum. Project description In comply with the clients requirements order to incr

  • Read More

  • Kayelekera Sulphuric Acid Plant

    From: August 2007
    To: January 2008
    Cost: R 152 million CAPEX on behalf of Paladin

    EP with Procurement for and on behalf of Client Project description As part of the complete Uranium Project currently being performed by Aveng E+PC for Paladin Resources in Malawi, a requirement for Sulphuric Acid Plant for the Leaching of the uranium ore arose. An enquiry went out to the market place for the supply of a 230 ton per day Acid Pl

  • Read More

  • Kayelekera Uranium Project

    From: March 2007
    To: January 2009
    Cost: $173 million

    EPCM of a Uranium Plant Aveng E+PC’s involvement in the Kayelekera Project commenced when Paladin Energy Limited requested Aveng E+PC to validate the bankable feasibility done by others, during which Aveng E+PC recommended that the CCD circuit be changed to a RIP and gypsum precipitation circuit. After the cost and process benefits of the re

  • Read More

  • Tarkwa Gold CIL Expansion Project

    From: November 2006
    To: September 2008
    Cost: $ 150 million

    Project description Gold Fields Ghana Limited approached Aveng E+PC to assist in expanding the current Tarkwa Gold Mine based in Tarkwa, Ghana. The goal was to increase the production of the existing CIL Plant from a feed rate of 450 000tpm to 500 000tpm by using various process solutions developed by Aveng E+PC. A further expansion of the plant

  • Read More

  • Afrisam Roodepoort Cement Mill 8 Project

    From: July 2006
    To: December 2008
    Cost: R 471 million

    Industrial EPCM Project Description Continued strong growth in the demand for cement in South Africa resulted in the Holcim Limited Board giving its final approval for the execution of the Roodepoort Cement Mill 8 Project on 3 November 2006. The project entails the provision of: A new 120t/hr Blending Plant A new 120t/hr Vertical Roller

  • Read More